Just a few quick updates:
-The house has a roof - with shingles!
-We have ALL the windows and doors installed (including the special block window in the master bath
-Tubs and showers are installed
-Air ducts are almost completely installed
-Plumbing lines are run all over the house
-The hardi plank siding has been delievered and is waiting to be installed
-Brick is ready - sand was delievered
We're going back tomorrow to take some pictures and make sure everything is in the right place...
Countdown about 55 days until it's supposed to be complete!!!! So exciting!